Is it expected behaviour when the end-time of an ongoing contributing booking is extended (via silent booking) that its resources are reconfigured again ?
Marieke Goethals [SLC] [DevOps Catalyst] Selected answer as best 5th July 2023
Hi Wale,
Which SRM Framework version are you running?
I had something similar in the past which is fixed since 1.2.28 > Problem when extending booking with pre-roll that had already started.
Wale Oguntoyinbo [SLC] [DevOps Enabler] Posted new comment 23rd May 2023
Hi Jens, that release does indeed describe the issue. However I’m running 1.2.30_CU2