Hi,
Is it possible to add a failover partner to existing DMA which already holds data?
Are there any special steps?
The failover partner will be empty.
Thanks
Marieke Goethals [SLC] [DevOps Catalyst] Selected answer as best 19th July 2023
Hi Craig,
This is possible. One of the requirements to configure a failover pair is to have an empty DMA. You can find additional information in Dojo:
Once the failover configuration has been set, the active DMA (the one that holds already data) will synchronize with the offline agent.