How does the DataMiner event scheduling adjust to datetime updates? In case a user entered a duration of the event, does the duration remain constant and unchanged even if there are clock updates during the event? Similar, in case a user enters a start/stop datetime for an event, does DataMiner shorten/extend the event?
KR, Steven
The duration takes into account the clock updates. If there is a clock update during the booking , the stop time will be set in such a way that the event duration is what has been defined at booking time.
Same applies when providing start/stop time: duration will be adjusted to reflect the real booking duration