Hi Dojo,
concerning the usage-based services, would it be imaginable to implement a functionality to set a spending limit to prevent costs from exceeding the available credits?
And, more generally, why is it possible to incur charges beyond the allocated credits in the first place, rather than having usage automatically capped once the credit limit is reached?
Thank you for some estimate!
Hi Nils!
Thanks for the question.
Both behaviours are intentional.
Why usage isn't capped when credits run out:
Many DataMiner systems run mission-critical operations. If a system stopped or lost functionality because a credit balance hit zero, that could cause serious disruption. So we chose to keep systems fully operational even when the available credit balance is empty. The only restriction today is that you can't create a new DaaS system until credits are topped up.
Why charges can go beyond your subscription:
I assume that by "allocated credits" you mean your subscriptions. The model is built for flexibility. Subscriptions cover your stable, committed usage at a discount. For example, if you know you'll need at least 10 connectors for the next 3 years, a 10-connector, 3-year subscription gets you a better rate.
Overage happens when your actual usage is higher than that baseline, for example during a peak or a temporary expansion. Nothing breaks. The extra usage is simply billed against your Pay Per Use (PPU) balance.
About a spending limit:
I see why an optional hard cap would be useful for budget control. I'll pass your request on to our sales team so they're aware of it and can take it into account.
Kind regards,
Brecht
Hi Brecht,
thank you very much for your answer! I suspected as such and I personally can follow that logic, but nevertheless I had to ask. 🙂
I want to suggest to provide some way to access the billing and consumption information, so monitoring of available credits (balance) as well as current consumption (current cost) is possible without explicitly logging in to dataminer.services manually.
Thanks again!